MARCH / APRIL 2021

BUILDINGS WITHIN PLOTS

 

PLOT 2

  • Demolitions, Excavations, Containment and Foundations completed
  • Drainage and Ground Slab concluded

  • Vertical Elements and 1st Level Slab – Completed

  • Vertical Elements and Intermediate and 2nd Level Slab – Completed
  • Vertical Elements and Housing Parking Slab – Completed 
  • Vertical Elements and ground floor housing slab – Completed
  • Vertical elements and 1st floor slab – Completed
  • Vertical elements and 2nd floor slab – Completed
  • Vertical elements and 3rd floor slab – Completed
  • Vertical elements and 4rd floor slab (last floor) – In execution
  • Masonry – initiated and in execution
  • The Excavations and Containment of the 3 north ramps to Av. Marechal Carmona have been completed
  • Vertical Elements and Slabs in Elevation of the 3 ramps have been completed

PLOT 4 (up to Silo)

  • Demolitions, Excavations and Containment completed
  • Foundations completed
  • Burried structures of the new supermarket technical area – concluded
  • Vertical elements and 1st level slab – concluded
  • Vertical elements and roof slab of the New Supermarket – concluded
  • Vertical Elements and Food Court Slab – concluded

COMMERCIAL PROJECT – PLOTS 2 AND 4

  • Finishes and Special Installations for Parking at Level 9.50 – concluded

 

The First Parking Lot of the New Auchan Hypermarket was inaugurated, with about 260 spaces, on 06/04/2021 by the President of CMC, Dr. Carlos Carreiras, and by the General Director of Auchan Retail Portugal, Eng.o Pedro Cid, who is currently in operation

Images provided by CMC

CURRENT SUPERMARKET IN EXPLORATION

  • Completed the 1st Stage of the Adaptation Works of the Current Supermarket – Conveyor Foundations
  • The 2nd Stage of the Adaptation Works of the Current Supermarket – Structural Reinforcement is in progress

PLOT 3

  • Demolitions, Excavations and Containment completed

  • Foundations completed

  • Vertical elements of 1st level nearing completion

GENERAL INFRASTRUCTURES

With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North Tunnel – Completed – It went into operation simultaneously with the opening of the New Car Park to the public (at 9.50 quota).
• South Tunnel – Structure in execution
• Intermediate tunnel – Structure in execution
• Remaining buried infrastructures ongoing

AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded
• Reprofiling started