JUNE 2021

BUILDINGS WITHIN PLOTS

 

PLOT 2

  • Reinforced concrete structure completed
  • Special installations and finishes in progress
  • External walls concluded
  • Interior walls in progress
  • Embedded Installations in progress
COMMERCIAL PROJECT – PLOTS 2 AND 4

UP TO AXIS 16 (SILO)

  • Quota 9.50 car park including access ramps completed

FROM AXIS 16 TO THE SOUTH

  • Silo Demolition completed
  • Partial demolition of the current hypermarket in progress

CURRENT SUPERMARKET IN EXPLORATION

  • Completed the Adaptation Works of the Current Supermarket 
PLOT 3

  • Demolition, Excavations and Contentions completed
  • Foundations completed
  • Vertical elements and 1st level slab completed
  • Vertical elements and 2nd level slab concluded
  • Vertical elements and 3rd level slab in progress

GENERAL INFRASTRUCTURES

With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North Tunnel – Completed – It went into operation simultaneously with the opening of the New Car Park to the public (at 9.50 quota).
• South Tunnel – Structure in execution
• Intermediate tunnel – Structure in execution
• Remaining buried infrastructures ongoing

AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded
• Reprofiling concluded