SEPTEMBER 2021
BUILDINGS WITHIN PLOTS
PLOT 2
- Reinforced concrete structure completed
- Special installations and finishes in progress
- External walls concluded
- Interior walls in progress
- Embedded Installations in progress
- Facade coating in execution
COMMERCIAL PROJECT – PLOTS 2 AND 4
UP TO AXIS 16 (SILO)
- Quota 9.50 car park including access ramps completed
- Finishes and Special Installations in execution
FROM AXIS 16 TO THE SOUTH
- Silo Demolition completed
- Partial demolition of the current hypermarket completed
- Foundations and Structures in execution
CURRENT SUPERMARKET IN EXPLORATION
- Completed the Adaptation Works of the Current Supermarket
PLOT 3
- Demolition, Excavations and Contentions completed
- Foundations completed
- Superstructure nearing completion
- Started exterior walls
- Started finishes and special installations
GENERAL INFRASTRUCTURES
With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA
AV. MARECHAL CARMONA
• North Tunnel – Completed – It went into operation simultaneously with the opening of the New Car Park to the public (at 9.50 quota).
• South Tunnel – Concluded
• Intermediate tunnel – Concluded
• Remaining buried infrastructures ongoing
AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded
• Reprofiling concluded
RUA HENRIQUE SEIXAS
• Infrastructure and reprofiling in progress