SEPTEMBER 2022
PLOT 1
- Construction started on this plot on July 4, 202
PLOT 2
- Completed reinforced concrete structure
- Special finishes and installations in progress
- Completed waterproofing
- Exterior walls completed
- Interior walls completed
- Wall and Floor coverings nearing completion
- Doors and Cabinets Wardrobes in progress
- Embedded Installations completed
- Facade cladding nearing completion
- Window frames and glazing nearing completion
- Special Installations nearing completion
- Kitchens and Appliances under assembly
- Outdoor arrangements / swimming pool in progress
COMMERCIAL PROJECT – PLOTS 2 AND 4
-
All Works concluded
-
Inauguration and Opening to the Public of the New Hypermarket held on 12.05.2022
PLOT 3
-
Completed reinforced concrete structure
-
Special finishes and installations in progress
-
Completed waterproofing
-
Exterior walls completed
-
Interior walls completed
-
Interior Wall and Floor Coverings in progress
-
Embedded Installations completed
-
Facade cladding nearing completion
-
Window frames and glazing nearing completion
-
Special Installations in progress
GENERAL INFRASTRUCTURES
- Deadlock on Rua José Joaquim de Freitas in progress
- With the exception of the deadlock at Rua José Joaquim de Freitas (access to the Central Shipyard and the works in progress on plots 2 and 3), and Jardim da Marginal Nascente (after the execution of plot 1), all general infrastructures were completed with the monitoring and approval of the various Public Service Concessionaires (Eredes, Galp Gás, Câmara Municipal de Cascais, Águas de Cascais, MEO)