APRIL / 2020

Buildings within Plots

PLOT 2

• Demolitions, Excavations, Containment and Foundations completed
• Drainage and Ground Slab in progress
• Vertical elements and 1st level slab – the vertical elements are completed and the shoring and formwork of the slab is started at elevation 13.00

PLOT 4 (up to Silo)

• Demolitions, Excavations and Containment completed
• Foundations practically completed

GENERAL INFRASTRUCTURES

With the monitoring, inspection and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CAMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North tunnel under development
• Remaining buried infrastructures ongoing

AV. MARGINAL
• Connection of Pluvial Sewer to Ribeira da Castelhana initiated