APRIL / 2020
Buildings within Plots
PLOT 2
• Demolitions, Excavations, Containment and Foundations completed
• Drainage and Ground Slab in progress
• Vertical elements and 1st level slab – the vertical elements are completed and the shoring and formwork of the slab is started at elevation 13.00
PLOT 4 (up to Silo)
• Demolitions, Excavations and Containment completed
• Foundations practically completed
GENERAL INFRASTRUCTURES
With the monitoring, inspection and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CAMARA MUNICIPAL DE CASCAIS, GALP ENERGIA
AV. MARECHAL CARMONA
• North tunnel under development
• Remaining buried infrastructures ongoing
AV. MARGINAL
• Connection of Pluvial Sewer to Ribeira da Castelhana initiated