FEBRUARY 2022

BUILDINGS WITHIN PLOTS

 

PLOT 2

  • Reinforced concrete structure completed
  • Special installations and finishes in progress
  • Waterproofing concluded
  • External walls concluded
  • Interior walls in progress
  • Embedded Installations in progress
  • Coating of facades and frames and glass in execution
  • Special Installations in execution

COMMERCIAL PROJECT – PLOTS 2 AND 4

  • All Works of the Construction Contract nearing completion
  • Fit-Outs started by Auchan
  • Started Tests, Receptions and Commissioning

PLOT 3

  • Demolition, Excavations and Contentions completed
  • Foundations completed
  • Superstructure nearing completion
  • Exterior walls completed
  • Waterproofing concluded
  • Finishes and Special Installations in execution

GENERAL INFRASTRUCTURES

With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North Tunnel – Completed – It went into operation simultaneously with the opening of the New Car Park to the public (at 9.50 quota).
• South Tunnel – Concluded
• Intermediate tunnel – Concluded
• Buried infrastructures of 1st phase completed
• Buried infrastructures of 2nd phase – Electrical networks

AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded
• Reprofiling concluded
• Dedicated Access Road to Av. de Sintra

RUA HENRIQUE SEIXAS
• Infrastructure and reprofiling completed
• Final pavement wear layer in preparation

AV. DE SINTRA

• Underground crossings completed
• Started reprofiling in the upward direction