JANUARY / 2021

BUILDINGS WITHIN PLOTS


PLOT 2

  • Demolitions, Excavations, Containment and Foundations completed
  • Drainage and Ground Slab concluded

  • Vertical Elements and 1st Level Slab – Completed

  • Vertical Elements and Intermediate and 2nd Level Slab – Completed
  • Vertical Elements and Housing Parking Slab – Completed 
  • Vertical Elements and ground floor housing slab – Completed
  • Vertical elements and 1st floor slab – Completed
  • Vertical elements and 2nd floor slab – Completed
  • Vertical elements and 3rd floor slab – In execution
  • The Excavations and Containment of the 3 north ramps to Av. Marechal Carmona have been completed
  • Vertical Elements and Slabs in Elevation of the 3 ramps have been completed

PLOT 4 (up to Silo)

  • Demolitions, Excavations and Containment completed
  • Foundations completed
  • Burried structures of the new supermarket technical area – concluded
  • Vertical elements and 1st level slab – concluded
  • Vertical elements and roof slab of the New Supermarket – concluded
  • Vertical Elements and Food Court Slab – In Execution

COMMERCIAL PROJECT – PLOTS 2 AND 4

  • Finishes and Special Installations for Parking at Level 9.50 – In execution

PLOT 3

  • Works have been initiated

CURRENT SUPERMARKET IN EXPLORATION

Completed the 1st Stage of the Adaptation Works of the Current Supermarket – Conveyor Foundations

 GENERAL INFRASTRUCTURES

With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North tunnel – Cloncluded structure
• South Tunnel – Structure in execution
• Intermediate tunnel – Structure in execution
• Remaining buried infrastructures ongoing

AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded