JUNE / 2020
Buildings within Plots
PLOT 2
• Demolitions, Excavations, Containment and Foundations completed
• Drainage and Ground Slab concluded
• Vertical Elements and 1st Level Slab – Completed
• Vertical Elements and Intermediate and 2nd Level Slabs – In great progress
• The Excavations and Containment of the 2 north ramps to Av. Marechal Carmona have been completed
• Excavation and ramp 3 containment have begun.
PLOT 4 (up to Silo)
• Demolitions, Excavations and Containment completed
• Foundations completed
• Burried structures of the new supermarket technical area – concluded
• Vertical elements and 1st level slab – In progress
CURRENT SUPERMARKET IN EXPLORATION
Adaptation works started, for future operation with adapted layout
GENERAL INFRASTRUCTURES
With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA
AV. MARECHAL CARMONA
• North tunnel under development
• Excavations and South Tunnel containment under development
• Remaining buried infrastructures ongoing
AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded