MAY / 2020

Buildings within Plots

PLOT 2

• Demolitions, Excavations, Containment and Foundations completed
• Drainage and Ground Slab concluded
• Vertical elements and 1st level slab – the vertical elements have been completed and the shoring, formwork and concreting of the slab at elevation 13.00 are in progress
• Practically completed the Excavations and Containment of the access ramps to Av. Marechal Carmona

PLOT 4 (up to Silo)

• Demolitions, Excavations and Containment completed
• Foundations completed
• 1st Level vertical elements started

GENERAL INFRASTRUCTURES

With the monitoring, inspection, and follow-up of public service concessionaires – EDP, PT, ÁGUAS DE CASCAIS, CÂMARA MUNICIPAL DE CASCAIS, GALP ENERGIA

AV. MARECHAL CARMONA
• North tunnel under development
• Excavations for the South Tunnel started
• Remaining buried infrastructures ongoing

AV. MARGINAL
• Pluvial Sewer Connection to Ribeira da Castelhana concluded