MAY 2022
BUILDINGS WITHIN PLOTS
PLOT 2
- Reinforced concrete structure completed
- Special installations and finishes in progress
- Waterproofing concluded
- External walls concluded
- Interior walls concluded
- Embedded Installations concluded
- Coating of facades in execution
- Frames and glasses next to conclusion
- Special Installations in execution
PLOT 3
- Demolition, Excavations and Contentions completed
- Foundations completed
- Superstructure nearing completion
- Exterior walls completed
- Waterproofing concluded
- Interior walls concluded
- Finishes and Special Installations in execution
GENERAL INFRASTRUCTURES
With the exception of the deadlock at Rua José Joaquim de Freitas (access to the Central Shipyard and the works in progress on plots 2 and 3), and Jardim da Marginal Nascente (after the execution of plot 1), all general infrastructures were completed with the monitoring and approval of the various Public Service Concessionaires (Eredes, Galp Gás, Câmara Municipal de Cascais, Águas de Cascais, MEO)