NOVEMBER 2022
PLOT 2
- Currently, the construction of residential plot 2 is in the final finishing phase with a view to obtaining authorization for use by the licensing authorities
COMMERCIAL PROJECT – PLOTS 2 AND 4
-
All Works concluded
-
Inauguration and Opening to the Public of the New Hypermarket held on 12.05.2022
PLOT 3
- Finished reinforced concrete structure
- Finishing and special installations in progress
- Completed waterproofing
- Completed exterior walls
- Completed interior walls
- Interior wall and floor coverings nearing completion
- Completed Embedded Installations
- Finished cladding of facades
- Frames and Glass in completion phase
- Special Installations in progress
GENERAL INFRASTRUCTURES
- Impasse at Rua José Joaquim de Freitas to enter plot 2 completed
- With the exception of the infrastructure connecting plot 1 and the Jardim da Marginal Nascente, to be carried out with the conclusion of plot 1, all general infrastructures were completed with the monitoring and approval of the various Public Service Concessionaires (E-redes, Galp Gás, Câmara Municipality of Cascais, Águas de Cascais, MEO)